Maui Water Master Plan

The same ideas behind the Tijuana River plan, applied at home on Maui: treat wastewater with less odor and less energy, reuse every drop we can, and turn sewage solids into products instead of a smell.

Private and early-stage. This is a community proposal by Rescuer Robots. It is not a County of Maui or State of Hawaiʻi plan.
Where Maui stands

Lahaina’s plant today

  • The Lahaina Wastewater Reclamation Facility makes about 3.1 million gallons a day of R-1 recycled water, with about 60% reused (County, February 2026).
  • Its solids handling is being upgraded: centrifuges replaced with screw presses and a covered sludge loadout (State Department of Health notice, October 2026).
  • About 200,000 gallons of partially treated wastewater overflowed during a March 2026 kona storm.
  • Residents still report sewage odor in parts of Lahaina.
Sources: Maui Alert, Feb 5, 2026; Hawaiʻi DOH, Oct 2026; Maui News, Mar 23, 2026.
The idea

From odor to value

Less odor

Map the spots where people smell sewage and target fixes there first.

Solids to products

Study turning dewatered sludge into compost, biochar, or biogas instead of landfill.

Ponds and wetlands

Explore Oswald–Green style ponds and constructed wetlands for polishing and habitat.

Cost-benefit, Maui

What sludge-to-energy could be worth

Today, Maui County's sewage sludge is ground up with green waste and grease-trap waste and buried at Central Maui Landfill. Composting there ended on March 1, 2020.

ItemFigureSource
County biosolids and grit landfilled20,080 tons (FY2024)State LUC report
Grease-trap waste landfilled5,920 tons (FY2024)State LUC report
Landfill space leftCapacity to about 2030State LUC report, 2026
Digester output proposed in 20184.5 million kWh a yearThe Maui News, 2018
Price proposed in 201829¢/kWh for 20 yearsThe Maui News, 2018
Maui home power, Nov 2026$254.08 for 500 kWh (50.8¢/kWh)Hawaiian Electric filing
Maui fuel charge, Nov 202630.19¢/kWhHawaiian Electric filing

The math

  • Power: 4,500,000 kWh ÷ 8,760 hours = about 0.51 MW running around the clock.
  • Cost under the 2018 offer: 4,500,000 kWh × $0.29 = about $1.3 million a year.
  • Oil it could displace: 4,500,000 kWh × $0.3019 fuel charge = about $1.36 million a year.
  • Same power at the Nov 2026 home rate: 4,500,000 kWh × $0.508 = about $2.29 million a year.

Benefits not priced here

Landfill space saved, less odor, heat to dry sludge, and digestate for compost or soil.

Estimate only. The 2018 proposal was never built, and it needed energy crops as well as sludge. Building and running costs for a Maui digester haven't been estimated yet. Rates change monthly. This isn't engineering or financial advice.

Live on Maui and smell it too?

Tell us where, and help shape the plan.